In recent years, the global refrigeration market has boasted broad prospects and witnessed rapid development. Refrigeration installation companies have also been constantly developing and growing. However, this has also brought about significant problems, such as low safety of cold storage projects, failure to complete the cold storage construction period on time, and a very short service life of cold storage. Some irresponsible cold storage installation companies even randomly configure cold storage refrigeration equipment or rush the construction period without paying attention to the quality of cold storage. If this persists, it may have an impact on the reputation of the entire refrigeration industry. Xueyun Refrigeration has strict regulations for cold storage installation. While ensuring the construction period, it will also guarantee the quality, safety, energy conservation and environmental protection of cold storage. It is precisely because of these strict standards that Xueyun has been able to continuously expand and grow during its development over the past ten-plus years. Today, I'd like to introduce to you how our company determines the installation period of cold storage:
Installation Period of Cold Storage
1. Before constructing a cold storage, we will stock up on the refrigeration equipment for the cold storage. This will generally take about seven working days, including compressors, cold storage panels, cold storage condensing units, cold storage control systems and some other small cold storage accessories. Generally, we start purchasing equipment after signing the contract.
2. Besides, after we have these equipment ready, there will be a delivery period of one to two working days. This is mainly related to the distance to the cold storage installation site. The farther the distance is, the longer the cold storage delivery period may be. Generally speaking, the delivery period will not exceed three days. We will arrange delivery vehicles to send them directly to the cold storage installation base.
3. Finally, there is the installation and commissioning period of cold storage, which is usually about seven days. However, this also needs to be differentiated according to the size of the cold storage and the refrigeration method of the cold storage.
4. Some other factors will also affect the installation period of cold storage. For example, if the ground where the cold storage is to be installed is uneven, extra time must be spent on leveling the ground, or filling the ground with cement. If the transportation is inconvenient, the cold storage panels need to be carried by manpower, which will also take more time. Moreover, if the power supply for the cold storage is not in place, it will have an impact on the acceptance and commissioning of the cold storage.